LamaLo Technology Inc.
Other
Projects
![]()

CCGS Gordon Reid –
SAR Cutter (2 x 1832 kW): The CCGS Gordon Reid was delivered in 1990
by Versatile Pacific, in
The vessel was grounded. The propeller blades were broken, and the
propeller shaft and rudder stock were bent.
A visual inspection of the strut and sterntube bearings indicated no damages. The shaft was not excessively bent and the
shipyard straightened the shaft within tolerance. Welding repair was required on the top of the
strut frames, which were found to be cracked.
A propulsion shaftline alignment theoretical analysis and measurement
program was conducted. The alignment
condition was measured using optical, jack-up load, and strain gauge alignment
techniques. The port and starboard strut
bearings were found to be misaligned such that the aft ends of the bearings
were higher than the forward ends and they were horizontally skewed. This misalignment was consistent with the
damage observed to the shafting and propeller, and would have resulted in
damage to the bearings if operated under this condition. To correct for this misalignment the port and
starboard strut bearings were replaced with new bearings and realigned to be
concentric, parallel and in line with the gearbox output shaft.
With the vessel afloat, the shaft was
realigned by adjustment to the lineshaft bearing. The subsequent alignment measurements showed
acceptable loads on the gear shaft bearings.
The CCGS Gordon Reid underwent sea trial the in April 2004. It has been reported that no significant
shaft vibrations were present and all bearing temperatures were acceptable.
![]()

MV Oscar Dyson – NOAA Fisheries Research Vessel (1 x 2300 kW): National
Oceanic and Atmospheric Administration (NOAA) 40-Day endurance fisheries
research vessels (FRV40-1) are under construction at VTHalter Marine
The vessels have a single screw propeller configuration. The 5 bladed fixed pitch propeller is driven
by two tandem DC Motors, each rated at 1150 kW at 134 RPM. The propulsion shaftline length is about 49'
long, and is supported by one sterntube bearing, one intermediate shaft
bearing, and one support bearing on the thrust shaft. Each of the two motor rotor shafts is
supported by two bearings.
LamaLo Technology was contracted to conduct
a theoretical propulsion shaftline alignment and vibration analysis, provide
the propulsion shaftline installation and alignment procedures, and to measure
and assess the shaft torsional and lateral vibrations during sea trials. The strain gauge technique was used to
conduct the final alignment prior to chocking.
The 1st of 4 vessels is to be delivered in 2004.
![]()

CAPS
Motors and Test Motor
Physical Torque Calibration Vibration Measurements
Center for Advanced Power Systems (CAPS)
Test Bed (2 x 2500 kW): The Center
for Advance Power Systems (CAPS) Test Bed Facilities has been developed to
conduct applied research on marine propulsion motors. It consists of two tandem 2.5 MW AC Electric
motors driving a test motor. The AC
motors are used to replicate propeller loads on the test motor. LamaLo Technology Inc. (LLT) was contracted
for the following:
·